Page 98 - Peterson 85 Years and Going Strong
P. 98

 CORE VALUE: CUSTOMER FIRST
  Caterpillar was, indeed, busy building a strategic alliance with York International. They’d been watching the worldwide rental market—big contenders like Aggreko, G.E., Allston, and Sunbelt. All were full-service rental enterprises who offered generators, compressors, and temperature control. Cat realized that to compete they had to rent more than just generators.
“At the time, I didn’t know much about chillers,” says Roger Wood, then PPSI’s rental manager. “I knew what they were and what they did, but that was it. Stanford needed an additional four thousand tons of cooling capacity for six months. I discussed it several times with Matt George, York’s service manager. He found some units and we put together a bid package and got the job.” Wood hired Matt George as a contractor to config- ure, install, and maintain the three York chillers.
Stanford was in the middle of a building frenzy and needed to increase their load capacity to accommodate the additional growth. “I knew those chillers would be there longer than six months because of all the other work York was doing there,”says George.“But the university said it would take six months.That’s why Roger’s nerves were on edge.” A half-million dollars was a lot of money to lay out for six months’ rent. In the end, those chillers stayed at Stanford for two years. Peterson was able to recoup its initial investment and then some.
“Large campuses like Stanford, with loads of ten thousand tons or more, generally utilize a central cooling plant,” explains George, who hired on with Peterson a year later to lead its new temperature control efforts. “A central plant is the hub where all the water goes through to get chilled and then flows back out to cool off the buildings and server farms within a campus cooling loop. Our job was to add more capacity inside that plant to support their campus expansions. It was a big balancing act.”
 Roger Wood & Matt George
That initial contract grew into several more jobs for Peterson over the next few years. In 1998–99, Stanford built an ice farm to augment its chilled water facility. Peterson rented them ten more units for that project. It was part of a continuing effort to keep up with growth and elevate their central energy facility to the latest technology. When completed in early 2000, it was the third-largest ice plant in the world.
In 2003, the EPA declared refrigerants bad for the ozone and initiated a schedule of phase-outs. Stan- ford’s Energy Services group had foreseen the issue and sought out innovative technologies to comply with the impending mandate. They decided on an ice bank strategy using ice-on-pipe technology.“Steel coils were nothing new to the industry, but the concept of grow- ing ice on pipe was,” says Randy Young, Peterson’s TC specialist (2001–16), who worked for Baltimore Air-
coil on an earlier Stanford ice project before coming to Peterson. “Stanford’s ice farm is an off-peak thermal storage unit buried beneath one of their campus parking lots. It’s basically a four million-gallon water tank the size of half a football field, with 360 miles of tubing—formed into school bus-size banks or coils—stacked inside, thirty feet high. At night when electricity rates are cheapest, they pump a freezing glycol solution
96 | PETERSON: 85 YEARS AND GOING STRONG
  
























































































   96   97   98   99   100