going to be able to get the final concrete done on
that middle chute where all the big holes were, the
first year. Instead, we filled that big hole with RCC
and built sixteen-foot-high temporary sidewalls
so they could use the spillway during the winter.”
That winter turned out to be much milder than the
previous one, so the spillway never had to be used.
PHASE TWO (2018)
(L-R) Duane Doyle Sr., Bill Doyle, and Duane Jr. visited Oroville Dam
in August 2017 for Bill’s 87th birthday. He passed away six months later.
The original Oroville Dam construction was a key event in Bill’s early
career at Peterson.
smooth out with a small dozer, compact, and you’re
done. It’s thick like oatmeal, so you don’t normally
have to do any forming. And the dozers won’t sink
in it.” Kiewit crushed over 2.5 million tons of re-
claimed aggregate, primarily to make the one mil-
lion cubic yards of RCC it used for both spillways.
“From the beginning, we knew it was going to be
a two-season job to complete the spillway because
of the amount of work,” says Petersen. “We weren’t
At the start of Phase Two, Kiewit demolished
the temporary walls and floor slabs on the mid-
dle chute and crushed them for RCC. Then it was
all about getting the entire spillway fortified and
poured in construction-grade concrete, and com-
plete again by November 1. Kiewit installed thir-
teen 300-ton Liebherr cranes as an aerial transport
system up and down the 3,000-foot-long spillway.
“Crews built crane pads and set up the cranes stra-
tegically so they could all reach certain areas and
get the spillway and side walls up quickly,” says Ni-
par. “Those cranes moved everything—generators,
excavators, light towers—whatever was needed to
get the job done. The team also tied millions of
pounds of rebar on the walls and slabs and moved
them down the spillway by crane for placement.”
Left to right: Meticulous cleaning of bedrock to insure a clean bond between concrete and rock in September 2018; Breaking up the first season’s temporary walls
of roller-compacted concrete (RCC) in May 2018