Top to bottom: Main Spillway with Liebherr cranes as transport system
in September 2018; Pouring concrete on upper chute of main spillway at
night in October 2018; Placing RCC on emergency spillway splash-pad
in August 2018
December 1. “We had to re-phase how much of
the spillway would be permanently construct-
ed—versus temporarily—to get through the rainy
season,” said Whelan. “We also had to do a lot
more excavation in the deep crevasse, which would
require a significant amount more of roller-com-
pacted concrete (RCC) to fill the hole. And that
meant a lot more crushing. All that changed how
we procured our materials and the concrete we’d be
batching. It changed a lot of things.” Kiewit used
RCC as a temporary fix for the main spillway and
a permanent solution for the emergency spillway.
All of it was batched right there at the site using
on-site materials.
“Roller-compacted concrete is extremely durable,
just like concrete,” explains Nipar. “It’s a quick
placement you can load into off-road trucks, dump,
CHAPTER 22 | 351