Page 352 - Peterson 85 Years And Going Strong
P. 352
The real eye-opener for Whelan happened even
before he walked the site at Oroville. “We flew out
to our Northern California office for an internal
meeting to review what the job entailed, and then
met with Peterson to notify them of some rough
quantities of equipment we would need. When we
showed up at the San Leandro dealership, there
were twelve to fifteen guys sitting around the ta-
ble waiting for us. That meeting was when I really
started to get a feel for the monumental task ahead.
From that meeting, it was basically ‘get ready for
the long haul.’ ”
For Peterson, the mad dash was on to locate the
machines Kiewit needed. “Rich Fregulia was in-
strumental in getting us the equipment we need-
Rich Fregulia was instrumental in
getting us the equipment we needed. He
pulled some rabbits out of his hat for us.
– Joe Whelan, equipment supervisor, Kiewit
Infrastructure West Co.
(L-R) Duane Doyle Jr. with Kiewit’s Joe Whelan onsite in August 2017
350 | PETERSON: 85 YEARS AND GOING STRONG
ed,” says Whelan, of Peterson’s salesman. “I don’t
know where he went to get stuff, but he pulled
some rabbits out of his hat for us. He kept us in the
know on when we’d be receiving things. Peterson
also provided us with loaners while we were wait-
ing for our new equipment, which you just don’t
see very often.”
At its peak, Kiewit had over 1,000 pieces of equip-
ment on the dam, including 150 pieces of heavy
equipment, 100 pickups, 13 giant Liebherr cranes,
plus light towers, generators, and chillers. “We
brought equipment in from all over the nation and
Canada,” says Whelan. “The equipment never quit
rolling in all the way up through October of 2017.
Every time there was a quantity increase or they
wanted us to do something more, we would add
more equipment.”
PHASE ONE (2017)
Going in, Kiewit knew that time would be its big-
gest challenge. It had just five months to get both
spillways ready for the next rainy season. “Even be-
fore we started, we had a hundred people helping
us gear up for the job,” says Jeff Petersen, Kiewit’s
executive project director for the Oroville Spillway
Emergency Repair Project. “From estimating to
getting contracts reviewed to inspecting equip-
ment nationwide and getting it all mobilized. And
that was just getting started.” From there, Kiew-
it moved in and set up a support camp, complete
with offices, conference rooms, parts stock, repair
shop, parking lots—the works. And then began
the real job of excavating the dirt and debris left
over from the massive spill.
Kiewit had been on the job for a month when
DWR called in the team to discuss some revised
goals. The regulatory agencies wanted the main
spillway operational by December 1 instead of
December 30, the original deadline. That meant
the concrete work had to be completed by Novem-
ber 1 to allow it to cure for potential operation on