CALAVERAS DAM REBUILD (2011–2019)
The Calaveras Dam Replacement project began in late
2011 as a four-year, $300 million contract. It is the cor-
nerstone of San Francisco’s $4.8 billion improvement
program on the Hetch Hetchy Regional Water System.
The Calaveras Reservoir is the Bay Area’s largest drink-
ing-water supply, but it had been reduced to 40 percent
capacity in 2001 due to seismic concerns. Officials
worried that the structure might fail since it is situated
within 1,500 feet of the active Calaveras Fault line. The
joint-venture team of Dragados USA, Flatiron West, and
Sukut Construction began work on it in August 2011.
The mammoth project required:
•
excavating 7 million cubic yards of rock and soil
•
embanking 4 million cubic yards of material
•
constructing a 41,000-cubic-yard concrete spillway
•
laying 6,000 linear feet of 78-inch steel pipe
•
tunneling and constructing a 250-foot deep by 30-foot wide intake tower
Calaveras Dam Rebuild during (top) and after (above)
The dam was finally completed on May 28, 2019, with an $823 million price tag. Today, the 210-foot high
pyramid-shaped earthen structure is located just downriver and butts up against its ninety-four-year-old
predecessor. The reservoir now provides 31 billion gallons of drinking water to 2.5 million residents in Alameda,
Santa Clara, San Mateo, and San Francisco counties.